Monte Laa – building sites 3 and 5
Company | PORR Bau GmbH, PORR Design & Engineering |
Principal | Monte Laa building site 3, Monte Laa building site 5 |
Location | Vienna - Austria |
Type | Special civil engineering, Technical building services planning, Building Information Modeling (BIM), Tender management, Building preparation, Structural design, General planning |
Service duration | 01.2015 - 12.2017 |
Runtime | 01.2015 - 12.2017 |
A construction site presenting special challenges
Until the end of 2017, an office tower, two residential towers and two low-rise buildings will be erected in Vienna’s Monte Laa urban development area. The office tower will be 33 storeys high and partially extend over Vienna’s A23 inner-city motorway. The residential towers with their height of up to 100m will feature 32 and 21 storeys, respectively, the low-rise buildings up to ten.
PORR Bau GmbH serves as a general contractor in the framework of this new construction. PORR Design & Engineering has been commissioned with highly complex design tasks:
Superstructure
- Preliminary draft
- Draft
- Submission
- Execution statics
- Formwork design
- Reinforcement design
Technical building equipment
- Preliminary draft
- Draft
- Submission
The building site’s soil conditions required to execute the project on a pile and raft foundation and use the cut-and-cover construction method. The integration of central safety installations for all building parts was executed particularly well. Thus, power supply, sprinkler central and emergency power supply are optimally used by the entire building complex.